@@ -62,7 +62,7 @@ parameter configurable.
| Phase | Domain | Status | Review | Build | Committed |
|---|---|---|---|---|---|
| Phase 0: Scraping spike | backend | ✅ Done | ⬜ Pending review | ⏭️ N/A (research) | |
| Phase 0: Scraping spike | backend | ✅ Done | ⚠️ Pass with notes (Sonnet) | ⏭️ N/A (research) | ✅ 070e34b |
| Phase 1: Solution + Domain | backend | ⬜ Not Started | ⬜ | ⬜ | ⬜ |
| Phase 2: Storage | backend | ⬜ Not Started | ⬜ | ⏭️ Big Bang | ⬜ |
| Phase 3: Scraping | backend | ⬜ Not Started | ⬜ | ⏭️ Big Bang | ⬜ |
@@ -84,4 +84,29 @@ parameter configurable.
## Amendment Log
(empty)
### Amendment 1 — 2026-05-05 — Phase 8 strategy change (deferred — formal approval will be requested when Phase 8 begins)
**Type:** Modify upcoming phase (Phase 8 — Results loader)
**What changed:** Phase 8's original subplan assumed marathonbet.by exposes a public
results / archive page that we can scrape to back-fill `EventResult`s. Phase 0 spike
proved this endpoint does NOT exist (`/su/results` returns 404).
**Why:** Spike findings — see `spike/SCRAPE_FINDINGS.md` and the deviation note in
`plans/initial-implementation/phase-0-scraping-spike.md` (Handoff section).
**New approach (to be formalised when Phase 8 begins):** Maintain a "watch list" of
events whose `ScheduledAt + EstimatedDuration` is in the past but whose status is not
`Completed`. Poll those event-detail URLs every 5 min until either
`eventJsonInfo.matchIsComplete=true` (capture `resultDescription`, mark complete) or
the URL 404s (mark `ResultUnknown`). Optional fallback to flashscore/sofascore is a
Phase 8 design decision.
**Impact on existing phases:** Phase 4 (Application + Workers) may need a new
`ResultsWatchListPoller : BackgroundService` in addition to the previously planned
`UpcomingEventsPoller` and `LiveOddsPoller`. Phase 2 schema may need a `WatchStatus`
field on `Event` (`Pending | InWatchList | Completed | ResultUnknown`). Both will be
re-evaluated when Phase 8 starts.
**Status:** Logged — formal subplan revision and user approval will be requested at the
start of Phase 8 (per skill rule: "All amendments require explicit user approval before
taking effect"). Phases 17 do not depend on Phase 8's tactical implementation.